*********************************
There is now a CONTENT FREEZE for Mercury while we switch to a new platform. It began on Friday, March 10 at 6pm and will end on Wednesday, March 15 at noon. No new content can be created during this time, but all material in the system as of the beginning of the freeze will be migrated to the new platform, including users and groups. Functionally the new site is identical to the old one. webteam@gatech.edu
*********************************
Atlanta, GA | Posted: January 30, 2020
General:
*Construction truck traffic in this sector of campus.
*Normal working hours are Monday - Saturday 6:30 AM – 5:30 PM.
Phase I Building Construction (within project fence line):
*Masonry, windows, fiber and metal panels will be installed at Exhibition Hall.
*Major mechanical and electrical equipment will be set at the Exhibition Hall.
*Overhead and in-wall mechanical, electrical, plumbing inspections will be completed at the Exhibition Hall.
*Drywall and ceiling grid installation will commence at the Exhibition Hall.
*Masonry, windows, fiber and metal panels will be installed at the Pavilion buildings.
*Interior metal framing walls, overhead mechanical, electrical and plumbing will be completed at the Pavilion buildings.
*Windows, fiber cement and metal panels will be completed at the Café building.
* Drywall and ceiling grid installation will commence at the Café building.
*Underground domestic water and fire line service will be installed.
*Hardscapes including sidewalks and pavers will be installed.
Phase I Utilities/ Ferst Center Plaza Pathway:
*Hardscapes including sidewalks and pavers will be installed.
*Temporary pedestrian pathways approaching Ferst Center to ISYE lawn will be removed.
*Fencing will be modified to open up pathway from Ferst Center to ISYE lawn.
*Sidewalk closures affected by utilities work at Ferst Center pathways will be restored and opened 2/10/2020.
Hardscape Work near ISYE Building:
*A temporary sidewalk has been placed north of the fence to maintain access to the south doors at ISYE.
*The fencing configuration will be modified to open the new pathway on 2/10/2020.
Old OIT Engineering Building – Temp WREK Radio:
*Miscellaneous interior renovations including new walls, electrical, and HVAC work will be completed in early February
*Areas of the building’s adjacent parking lot will be dedicated to Contractors and logistics.