Campus Center Construction Update - December 2019

*********************************
There is now a CONTENT FREEZE for Mercury while we switch to a new platform. It began on Friday, March 10 at 6pm and will end on Wednesday, March 15 at noon. No new content can be created during this time, but all material in the system as of the beginning of the freeze will be migrated to the new platform, including users and groups. Functionally the new site is identical to the old one. webteam@gatech.edu
*********************************

Contact

For further information regarding this project contact:

Nicolas Palfrey

Capital Project Manager

Georgia Institute of Technology | Facilities Design & Construction

470-363-7520

Sidebar Content

The Campus Center Project will renovate portions of the existing Student Center and expand services into four new buildings across a 15-acre site to create program spaces necessary for the growing campus.

Summaries

Summary Sentence:

Construction Impacts for Campus Center during the month December 2019

Full Summary:

Campus Center construction continues through the month of December.

Media
  • Campus Center Construction Impacts - December 2019 Campus Center Construction Impacts - December 2019
    (image/png)
  • Campus Center Construction Impacts - December 2019 Campus Center Construction Impacts - December 2019
    (image/png)
  • Campus Center Construction Updates -  November  2019 Campus Center Construction Updates - November 2019
    (image/png)
  • Campus Center Construction Updates - November 2019 Campus Center Construction Updates - November 2019
    (image/png)
  • Campus Center Construction Updates - November 2019 Campus Center Construction Updates - November 2019
    (image/png)

In the month of December 2019, Phase I work including construction of the Exhibition Hall, Pavilion and Café buildings will continue for the Campus Center project. 

General:

*Construction truck traffic in this sector of campus.

*Normal working hours 6:30 AM – 5:30 PM.

Phase I Building Construction (within project fence line):

*Pre- Engineered Metal Buildings and roofing for Pavilion buildings will be erected.

*Exterior metal framing, sheathing, and waterproofing at Café building will be installed.

*Waterproofing, flashing, masonry and windows will be installed at Exhibition Hall.

*Overhead mechanical, electrical, and plumbing systems at the Exhibition Hall installation will continue.

*In- wall electrical and plumbing systems at the Exhibition Hall installation will continue.

*Underground domestic water and fire line service will be installed.

Phase I Utilities:

*Storm, sanitary sewer, and power ductbank will be installed north of the Student Center Parking Garage 9/6/2019 – 12/20/2019.

*Fencing will remain in place to provide barriers between construction activities and the campus.

*Signage will remain in placed around perimeter of fencing to direct pedestrian traffic. 

*Pedestrian pathways approaching Ferst Center from ISYE lawn have been installed to divert walkways around construction.

*Way finding signage has been placed around this part of campus to provide alternate routes.

*ADA pathways will be maintained from the parking lot in front of Student Services to Ferst Center for the Arts.

Phase II Existing Utilities Site Investigation:

 *At the Campanile Plaza area, site investigations to verify and confirm locations of existing underground utilities will be performed.

*Temp barricades and signage will be placed around work perimeter to direct pedestrian traffic.

*Small localized excavations using a hydrovac truck will be mobilized.

*The hydrovac truck will access the work area from the W21 parking lot.  Subsequently, 3 parking spaces in the extreme south end will be closed for staging.

*Small areas will be cut into the turf and landscape areas.  These areas will be backfilled and patched once investigations are complete.

*Site logistics plan is attached.

Old OIT Engineering Building – Temp WREK Radio:

*Miscellaneous interior renovations including new walls, electrical, and HVAC work will occur during the months of December and January.

*Areas of the building’s adjacent parking lot will be dedicated to Contractors and logistics.

 

Additional Information

Groups

Facilities Management

Categories
Institute and Campus
Related Core Research Areas
No core research areas were selected.
Newsroom Topics
No newsroom topics were selected.
Keywords