Campus Center Construction Updates - November - December 2019

*********************************
There is now a CONTENT FREEZE for Mercury while we switch to a new platform. It began on Friday, March 10 at 6pm and will end on Wednesday, March 15 at noon. No new content can be created during this time, but all material in the system as of the beginning of the freeze will be migrated to the new platform, including users and groups. Functionally the new site is identical to the old one. webteam@gatech.edu
*********************************

Contact

For further information regarding this project, contact 

Nicolas Palfrey

Capital Project Manager

470-363-7520

Sidebar Content

The Campus Center Project will renovate portions of the existing Student Center and expand services into four new buildings across a 15-acre site to create program spaces necessary for the growing campus.

Summaries

Summary Sentence:

Construction Impacts for Campus Center during the months of November and December 2019

Full Summary:

In the month of November 2019, Phase I work including construction of the Exhibition Hall, Pavilion and Café buildings will continue for the Campus Center project. 

 

Media
  • Campus Center Construction Updates - November 2019 Campus Center Construction Updates - November 2019
    (image/png)
  • Campus Center Construction Updates - November 2019 Campus Center Construction Updates - November 2019
    (image/png)
  • Campus Center Construction Updates - November 2019 Campus Center Construction Updates - November 2019
    (image/png)
  • Campus Center Construction Updates -  November  2019 Campus Center Construction Updates - November 2019
    (image/png)

General:

*Construction traffic in this sector of campus.

*Normal working hours 6:00 AM – 5:30 PM.

Phase I Building Construction (within project fence line):

*Pre- Engineered Metal Buildings and roofing for the Café and Pavilion buildings will be erected.

*Exterior metal framing, sheathing, and waterproofing at the Exhibition Hall will continue.

*Roofing at Exhibition Hall will be substantially complete.

*Exhibition Hall masonry and window systems installation will begin.

*Overhead mechanical, electrical, and plumbing systems at the Exhibition Hall will be installed.

*Interior metal framing walls and door frames will be installed at Exhibition Hall.

Phase I Utilities:

*Storm, sanitary sewer, and power ductbank will be installed north of the Student Center Parking Garage 9/6/2019 – 12/20/2019.  Work should pass Smithgall 11/15

*Fencing will remain in place to provide barriers between construction activities and the campus.

*Signage will remain in placed around perimeter of fencing to direct pedestrian traffic. 

*Pedestrian pathways approaching Ferst Center from ISYE lawn have been installed to divert walkways around construction.

*Way finding signage has been placed around this part of campus to provide alternate routes.

*ADA pathways will be maintained from the parking lot in front of Student Services to Ferst Center for the Arts.

 

 

 

 

 

 

Related Links

Additional Information

Groups

Facilities Management

Categories
Institute and Campus
Related Core Research Areas
No core research areas were selected.
Newsroom Topics
No newsroom topics were selected.
Keywords
Facilities-Notices, Campus Center, Campus Construction
Status
  • Created By: cbrim3
  • Workflow Status: Published
  • Created On: Oct 29, 2019 - 2:33pm
  • Last Updated: Oct 31, 2019 - 2:01pm