There is now a CONTENT FREEZE for Mercury while we switch to a new platform. It began on Friday, March 10 at 6pm and will end on Wednesday, March 15 at noon. No new content can be created during this time, but all material in the system as of the beginning of the freeze will be migrated to the new platform, including users and groups. Functionally the new site is identical to the old one. webteam@gatech.edu
*********************************
Atlanta, GA | Posted: May 13, 2019
Communication ductbanks will be installed across Dalney St. and Greenfield St. in order to re-route aerial cables to below ground.
Construction Start Date: Monday, May 13, 2019
Tentative Construction Completion Date: Friday, July 6, 2019
Impact:
· Parallel parking along Greenfield St. NW will be off-line from Monday, May 13th until Friday, May 24th.
· Traffic heading south on Greenfield St. NW will be temporarily re-routed to the drop-off lane at the GTRI Research Building North.
· Parallel parking along Dalney St. NW will be off-line from Monday, May 27th until Friday, June 7th.