Price Gilbert and Crosland Tower Renewal: November 2016 through January 2020

*********************************
There is now a CONTENT FREEZE for Mercury while we switch to a new platform. It began on Friday, March 10 at 6pm and will end on Wednesday, March 15 at noon. No new content can be created during this time, but all material in the system as of the beginning of the freeze will be migrated to the new platform, including users and groups. Functionally the new site is identical to the old one. webteam@gatech.edu
*********************************

Contact

Jessica Rose, Facilities Communication Officer

Gary Petherick, Construction Manager 

Sidebar Content
No sidebar content submitted.
Summaries

Summary Sentence:

The Dorothy M. Crosland Tower will be closed for nearly two years to undergo a complete renewal. Interior abatement has begun in some areas and pedestrian detours will change throughout construction phases. 

Full Summary:

The Dorothy M. Crosland Tower closed for nearly two years on December 31, 2015. Interior abatement has begun in some areas and pedestrian detours will change throughout construction phases. 

Media
  • LibraryNext 2017 Construction Map LibraryNext 2017 Construction Map
    (image/jpeg)
  • Library construction - January 2017 Library construction - January 2017
    (image/jpeg)
  • Library construction - January 2017 Library construction - January 2017
    (image/jpeg)

CONSTRUCTION DETAILS:

  • Start Date: November 1, 2016
  • Anticipated End Date: January 30, 2020

Normal Working Hours: 7am-5pm. Weekend work will only be necessary in there are major rain delays.

 

Campus Detours or Interruptions:

Phased detours of pedestrian traffic will occur around the Library complex, corresponding the construction sequences.

November 2016-2017: Work will close the north sidewalk of Bobby Dodd Way between Old Civil Engineering Building, Cherry Street and the alley between Old Civil Engineering building and Crosland Tower.

July 2017-November 2018: Work will close described above and also pedestrian way between Bobby Dodd Way/Cherry Street to Fourth Street between Price Gilbert and Crosland Tower. Access to Hinman and Rich will be maintained from Fourth Street but not o he north side of the Price Gilbert Library.

 

RENEWAL BENEFITS: 

  • Improved accessibility and/or ADA Compliance
  • This project is an Adaptive Reuse and meets sustainability goals
  • Added seating and study space for students
  • New technology tools will support learning goals

 

USER DETAILS:

All computers, scanners, printers, study spaces and other resources in Crosland will move to Price Gilbert, also known as Library West. More information can be found at http://renewal.library.gatech.edu/ 

Related Links

Additional Information

Groups

Facilities Management

Categories
Institute and Campus
Related Core Research Areas
No core research areas were selected.
Newsroom Topics
No newsroom topics were selected.
Keywords
Georgia Tech Library and Information Center, librarynext, Facilities Management, Facilities-Notices, Facilities-detour, buidling construction
Status
  • Created By: Jessica Rose
  • Workflow Status: Published
  • Created On: Nov 16, 2016 - 10:41am
  • Last Updated: Jan 26, 2017 - 2:36pm