There is now a CONTENT FREEZE for Mercury while we switch to a new platform. It began on Friday, March 10 at 6pm and will end on Wednesday, March 15 at noon. No new content can be created during this time, but all material in the system as of the beginning of the freeze will be migrated to the new platform, including users and groups. Functionally the new site is identical to the old one. webteam@gatech.edu
*********************************
Atlanta | Posted: October 13, 2016
Improved accessibility and/or ADA Compliance
· Historic Building
· Adaptive Reuse
· Safety and/or Lighting Improvements
· Green Space and/or Open Space
· Added Seating
CONSTRUCTION DETAILS:
· Start Date: November 1, 2016
Normal Working Hours: 7am-5pm. Weekend work will only be necessary in there are major rain delays.
· Anticipated End Date: January 30, 2020
Campus Detours or Interruptions:
Phased detours of pedestrian traffic around the Library complex corresponding to the construction sequences.
November 2016- Summer 2017: Work will close the north sidewalk of Bobby Dodd Way between Old Civil Engineering Building, Cherry Street and the alley between Old Civil Engineering building and Crosland Tower.