There is now a CONTENT FREEZE for Mercury while we switch to a new platform. It began on Friday, March 10 at 6pm and will end on Wednesday, March 15 at noon. No new content can be created during this time, but all material in the system as of the beginning of the freeze will be migrated to the new platform, including users and groups. Functionally the new site is identical to the old one. webteam@gatech.edu
*********************************

Contact

Jessica Rose
Communications Officer
Facilities Management
404-385-1822

CONSTRUCTION PROJECT MANAGER: Gerald Shumake

Sidebar Content
No sidebar content submitted.
Summaries

Summary Sentence:

Atlantic Promenade South will undergo construction to replace aged steam lines and upgrade adjacent hardscape and landscape.

Full Summary:

The repairs require significant digging, which provides an opportunity to enhance the pedestrian experience through the primary north/south corridor of campus on Atlantic Drive. 

Media
  • Atlantic Drive Corridor: Future State Atlantic Drive Corridor: Future State
    (image/jpeg)
  • Atlantic Drive Construction Map 2 Atlantic Drive Construction Map 2
    (image/jpeg)

Atlantic Promenade South will undergo construction to replace aged steam lines followed by upgrades to adjacent hardscape and landscape. The repairs require significant digging, which provides an opportunity to enhance the pedestrian experience through the primary north/south corridor of campus on Atlantic Drive. The project will create a connected, walkable corridor envisioned in the campus master plan and landscape master plan. This will provide for a safer campus by providing better lighting, eliminating trip hazards and improving accessibility within the area.

  • New steam lines to Bunger Henry and Van Leer buildings
  • New steam service running up to Atlantic Drive
  • Improved landscape and hardscape
  • New walkway
  • Better lighting
  • Elimination of trip hazards

CONSTRUCTION DETAILS:

  • Start Date: March 1, 2016
  • Normal working hours: Monday through Friday, 7 a.m. – 5 p.m. with more disruptive work restricted to after 9 a.m. Weekend work will only be necessary if there are major rain delays.
  • Anticipated End Date: December 2016

Campus Detours or Interruptions:
Pedestrian access to Atlantic Drive will be unavailable from the Mason Building Area, all the way to Tech Green. Access to all buildings will remain open. Please follow signage. 

Related Links

Additional Information

Groups

Administration and Finance

Categories
Institute and Campus, Community
Related Core Research Areas
No core research areas were selected.
Newsroom Topics
Campus and Community
Keywords
detour, Facilities Management, Facilities-detour, Facilities-Notices, Georgia Tech Library, streetscapes, utilities
Status
  • Created By: Jessica Rose
  • Workflow Status: Published
  • Created On: Feb 12, 2016 - 10:36am
  • Last Updated: Oct 7, 2016 - 11:20pm